Logisticspark.
Transfera Logistics Park (TLP) and logistics center TLC1
TLP, TLC1
In June 2021 Transfera announced the start of construction of its first logistics center (TLC 1), as part of a broader project to create a Transfera Logistics Park (TLP). The location is 30 km from Belgrade and 20 km north of Belgrade Airport, in Novi Banovci, near the E-75 highway, 4 km from the intermodal terminal in Batajnica.
In a record nine months, Transfera finished construction of TLC1. The first logistics center covers 30,000 m², of which 3,000 m² are office space, while the rest is storage space and facilities for recreation and relaxation such as restaurants, cafes, a cafeteria for employees and a trim track.
The facility is equipped with a Warehouse management system (WMS), applying the highest FM Global standards, and one of the priorities is the use of renewable energy sources. The 53,000 m² terminal on which TLC1 is built is operated with the Yard management system (YMS) and Dock management system (DMS).
TLC1 officially opened on 11 September 2022.
- Location, 30 km from Belgrade, 20 km north of Belgrade Airport, near the E-75 highway
- Novi Banovci
- Address (TLC head office)
- Druga logistička 14, 22304 Novi Banovci
- Distance to the intermodal terminal in Batajnica
- 4 km
- TLC1 area
- 30,000 m²
- Office space in TLC1
- 3,000 m²
- Total terminal area on which TLC1 is built
- 53,000 m²
- Start of TLC1 construction
- June 2021
- TLC1 construction time
- 9 months
- TLC1 grand opening
- 11 Sep 2022
- Warehouse, yard and dock management software
- WMS, YMS, DMS
- Rooftop solar project on TLC1 with Green Energy 360 (2023)
- Solar panels
- Storage capacity increase (history, 2024)
- +10,000 m²
- Capacity of the sorting machine in the logistics center (99.8% accuracy)
- 90,000 parcels per day

Warehouse, yard and docks in one system.
WMS, YMS and DMS software run the warehouse, yard and docks of logistics centre TLC1.
The centre.